§ 1503. Referral and action
A.
Within fifteen (15) working days after submission of the site plan, the building official shall review the site plan. If the director determines that the site plan cannot be approved without the granting of a variance or use permit, or the enactment of an amendment to this ordinance, the building official shall inform the applicant and shall not act on the application until proper application for a variance or an amendment has been filed with the city and acted upon as prescribed by this ordinance.
B.
Except as provided under subsection 1503.A above, or if a longer period is required to meet the requirements of section 1508, within 25 working days after the submission of the site plan, the planning commission shall approve, with conditions, or disapprove the site plan. In approving the site plan, the commission shall make the findings prescribed under section 1505.
C.
The approved site plan, with any conditions shown thereon or attached thereto, shall be dated and signed by the building official, with one copy mailed to the applicant and one copy filed with the building official.
D.
Revisions by the applicant to an approved site plan shall be resubmitted to the building official in the manner required for drawings first submitted.
(Ord. No. 2015-01, § 1, 4-8-2015)