§ 1704. Referral and action
A.
The building official shall check all drawings submitted for architectural design review for compliance with applicable provisions of this code, and shall submit the drawings to the ADRC. If the building official determines that a design review permit cannot be issued without the granting of a variance, use permit or amendment to this ordinance, the building official shall inform the applicant and shall not submit the drawings to the ADRC until such variance, use permit or amendment is first applied for and approved by the city.
B.
The authority of the ADRC with respect to building design and improvement shall extend to reviewing plans and making recommendations which require voluntary compliance by the applicant.
C.
The ADRC shall act to approve, deny or require modification of the drawings submitted for committee review within forty (40) days of the determination by the building official that the application meets the requirements of this article for submission.
D.
Reports and recommendations of the ADRC shall have the concurrence of at least three (3) voting members of the committee and shall be reported to the applicant in writing within ten (10) days after the committee's action.
(Ord. No. 2015-01, § 1, 4-8-2015)